Topical Issues

March 18, 2019

In the framework of the project «Increasing the production capacity of thermoplastic elastomers from 50 to 100 thousand tons per year», a separate subdivision «Voronezh» of Promstroi made installation of three MS-201 reactors - D, E and F on title 200 (Polymerization unit). Installation was carried out under the conditions of the existing installation. The weight of each reactor is 52 tons, height - 12 m, diameter - 5 m.
In total, 69 units of technological equipment, 329 tons of steel structures, 2757 cubic meters of concrete were poured, 599 meters of engineering networks were laid, 2643 inches-diameter of technological pipelines joints were installed in the area of responsibility of Promstroi JSC.
The facility mobilized 124 personnel workers (including machine operators), 7 units of heavy equipment. Total percentage of readiness - 28.2%.


March 15, 2019

At the plant for the production of polypropylene with a capacity of 500 thousand tons per year, the General contractor for the construction of which was JSC PROMSTROI, a flare unit designed for burning emergency discharges, periodic and permanent, was put into operation. The height of the torch is 96 m, weight 180 tons. To ensure smokeless combustion, medium-pressure steam is supplied to the head of the flare barrel. In order to avoid explosive atmosphere, the flare barrel is continuously blown by natural gas or nitrogen.


March 13, 2019

At the installation of polypropylene «Zapsibneftekhim» received the first granules of products!
Progress in the construction of the polypropylene unit of the complex under construction for deep processing of hydrocarbon raw materials «Zapsibneftekhim» reached 99.8%. The General contractor of the construction was JSC «Promstroy». Construction and installation works have been completed at the technological installation, and commissioning works have been completed in the active phase. In particular, functional tests of systems, check of operability of security systems are conducted.
As part of the pre-commissioning works in the test mode, the first polypropylene granules from imported raw materials were obtained.
The technology allows to produce all types of polypropylene presented in all market segments.After the launch of Zapsibneftekhim, the total volume of polypropylene produced at SIBUR's Tobolsk enterprises (including SIBUR Tobolsk's existing polymer production) will amount to 1 million tons of polypropylene per year. This is the largest capacity in Russia and one of the largest in the world.


February 20, 2019

The separate division “Omsk” Promstroi JSC produced the first installation of the equipment for the V-105 cooling system capacity (Title 7826) at the Omsk Refinery. The device is intended for reception, storage and distribution of kerosene.
Recall, Promstroi JSC performs construction and installation work as part of a large-scale modernization program for the Omsk Gazpromneft refinery.


February 11, 2019

Promstroi JSC continues to supply materials and equipment for the construction of the Amur Gas Processing Plant of Gazprom (the investor and customer of the project is Gazprom Processing Blagoveschensk), which will become the largest in Russia and the second largest in the world in natural gas processing. In the area of responsibility of the supplier - materials and equipment of the plant general production facilities.
At the end of 2018, 23 thousand tons of steel structures were delivered to the construction site of the AGPZ, which is 58% of the total planned volume, also 19 thousand tons of large-diameter pipes. Supply of seamless pipe, elbows and fittings has been completed. At the moment, Promstroi cooperates with more than 10 suppliers of metal structures, cable and pipe products.


February 01, 2019

As part of the project «Increasing the production capacity of thermoplastic elastomers from 50 to 100 thousand tons per year» on January 31, the forces of OP «Voronezh» JSC «Promstroi» was made filling the slab «Installation of purification of industrial effluents from lithium ions (Title 460)» in the amount of 110 m3 concrete.
Also earlier in the «Site decontamination» (Title 300) in the current setup produced the technically-challenging installation of degassers, MS-311/2 and MS-312/2 with the dismantling of steel structures and the removal of the roof. The height of each device is 12 m, diameter - 4 m.
In total, 41 units of equipment have been installed at the facility in the area of responsibility of JSC Promstroi.


January 21, 2019

Supply of equipment and materials for the construction of the entire complex is 98.9%. Construction and installation works have been completed by 92.4%.
Progress of works on installations in the area of responsibility of JSC "Promstroy" according to the official data of the Customer-SIBUR Tobolsk:

  • Installation of polypropylene-99,6%
  • Off-site facilities – 95,1%
  • Logistics platform-99.7%.

The main events of the month at our facilities:

The installation of polypropylene::

  • loading of test pellets for the pellet transportation system from extrusion to homogenization silos
  • the powder pneumatic conveying system has been checked and set up
  • the extrusion line a is ready for pre-commissioning.

On the objects of General factory economy: installation of the main technological equipment has been completed in industrial parks.

Zapsibneftekhim is a logical stage in SIBUR's development in the West Siberian region. Over the past 10 years, the capacity for gas fractionation of the Tobolsk site has been significantly expanded, the shflu-wire from the Purovsky plant to SIBUR Tobolsk has been built, and the capacity of the non-public Denisovka station of the Sverdlovsk railway has been doubled.
Zapsibneftekhim will become the largest modern petrochemical complex in Russia and involves the use of the latest advanced technologies in the field of hydrocarbon processing and logistics, which will ensure the reliability, safety and efficiency of the investment project.
Information and photo - https://zsnh.sibur.ru .


January 14, 2019

On December 15, 2018, ahead of the contractual period of 4 months, ZapSibNeftekhim LLC and Promstroy Group JSC signed a mechanical readiness act for the production of commissioning and commissioning of the facility for a polypropylene production unit with a capacity of 500 thousand tons per year. Congratulations to all involved colleagues!


More news

PSG is a member of the RF CCI

 

 

 

About PSG

Promstroi Group of Companies is a construction and installation Holding Company performing design and construction of large-scale industrial projects of power-producing industry (oil & gas processing, transportation and storage facilities), power industry and metallurgy industry.

Industrial segments:

  • Oil & gas (upstream, midstream, downstream)
  • Power engineering
  • Metallurgy

More than 10 specialized companies in Russia, Kazakhstan and Belarus.

Mission

Development of energetic industry in Russia and Kazakhstan.

Strategy

Creation of open, independent, successfully managed Company – leader in the sphere of industrial construction in Russia – by means of the combination of the best Russian and international practices, as well as its own integrated project & assets management system.

Main Services

  • Engineering
  • Project management - General contract, ()
  • Construction and installation works:
    • Civil works
    • Construction of main and field pipelines, well pads and on-site roads
    • Installation works (installation of technological equipment and industrial pipelines, metal structures, power supply and automation systems)
  • Commissioning
  • Metal structures production

Key Success Factors

  • Team of managers and specialists with the same understanding of business, values and contracting risks
  • Unique combination of assets acquired within the framework of the strategy realization of Promstroi Group of Companies
  • Project-oriented resources/efficiency/liquidity management system
  • Company Management System complying with the requirements of ISO 9001:2015, ISO 14001:2015, OHSAS 18001:2007
  • Securing of contractual obligations by guarantees provided by Sberbank of the Russian Federation
  • Pool of reliable subcontractors and suppliers

More

 


 

Promstroi Group
of Companies


 

PROMSTROI-GROUP
JSC

Moscow

 
 

Subsidiaries

 

Promstroi
JSC

Nyagan (KMAD)

 

Spetsializirovannoye
Upravlenie No.6
JSC

Stavropol

 

Uralmontazhavtomatika
OJSC

Tyumen

 

KAZMEKHANOMONTAZH
LLP

Republic of Kazakhstan,
Almaty

 

Novopolotsk Metal
Structures Plant
JV LLC

Republic of Belarus,
Novopolotsk

 

Inzhpromstroi
LLC

Blagoveshchensk

 

Associated
undertakings

Talspetsstroi
LLC

Nyagan (KMAD)